BC real estate · long read
The silent tower, the barber, and the law that decides who keeps the unit
Eclipse at Lumina Brentwood has its occupancy permit, and on August 25, 2026 its presale buyers won in court. The man who built it came to Canada as a pharmacist who couldn't get credentialed; by 2023 the Province credited him with more than $4 billion in development and named him to the Order of British Columbia. More than three dozen of his customers asked the BC Supreme Court to hold that his contracts could not be enforced against them, and the court agreed. What it decided will shape what every other stranded BC presale buyer can do for the rest of this decade.
Published June 3, 2026 · Updated October 13, 2026
The silent tower
At 2381 Beta Avenue in Burnaby, the Eclipse at Lumina Brentwood is a thirty-four-storey concrete tower that sat at roughly 95 percent complete through the receivership and received its occupancy permit on April 10, 2026. There are 329 units inside it (per Thind Properties' filings; KingSett's filings cite 335). 232 of them were pre-sold over 2021, 2022, and 2023. From the corner, the building looks finished: glass on most of the floors, balconies in place, the tall slab silhouette typical of any Brentwood mid-cycle project.
The City of Burnaby suspended the building permits in November 2024. Construction stopped. KingSett Mortgage Corp., the senior lender, was owed $189 million on Eclipse alone as of December 27, 2024 (a figure that had climbed to roughly $225 million by December 2025) and $500 million across the developer's broader portfolio of stalled BC residential projects, with interest accruing at approximately $54,000 per day. The crane at the top is still up. Construction was "deemed substantially complete" by mid-March 2026; an occupancy permit was issued on April 10, 2026.
According to BC Assessment, the assessed value of the Eclipse tower fell from $257 million in July 2024 to $185 million in July 2025. Nearly seventy million dollars of that drop was in the value of the building itself.
The unresolved question is whether the eventual occupant of each of those units will be the original presale buyer, the senior lender, an institutional investor, or (increasingly likely for many of the units) a court-supervised receiver running a structured sales process and pocketing the difference between the 2022 presale price and the 2026 resale value.
The man who built it
The developer's name is Daljit Thind. He was born in the village of Rachian, in the Ludhiana district of Punjab, and earned a Bachelor of Science from Rohtak University with the intention of pursuing pharmacy. He moved to Burnaby in 1990, according to the Province, where his Indian credentials did not transfer for professional licensing. He took work as a tile layer, then moved across the other trades. He kept working.
According to a BIV profile, he bought a vacant lot in Surrey, built a house on it with a partner, and lost about fifteen thousand dollars. He kept building, from single-family homes to mid-rise condominium projects to the concrete towers that have been the centre of his portfolio for the last decade.
On August 7, 2023, the Province of British Columbia named Daljit Thind to the Order of British Columbia, the highest civilian honour the province confers, citing his record as a developer and his contributions to housing supply in the Lower Mainland.
Seventeen months later, his company entered creditor protection in BC Supreme Court.
The tax bill nobody told the buyers about
The collapse, like most collapses, was visible to the people closest to it long before it was visible to anyone else. On June 30, 2023, five weeks before the Province would announce Thind's Order of BC on August 7, the Canada Revenue Agency registered an $11,996,763 judgment against the Eclipse-related corporate entities. KingSett would later allege, in subsequent court filings, that $7.5 million in GST collected on a related Thind project, Highline at Metrotown, had been misappropriated, diverted from the trust accounts it was meant to be held in. The court-appointed monitor, KSV Restructuring, would later state on the record that the alleged misuse of those funds was never substantiated; the allegation and the rebuttal now sit side by side in the public CCAA file. By the end of 2023, the company's senior secured lender was preparing for the worst.
The 2023-cohort of Eclipse presale buyers did not know any of this. Several of them, in particular, continued to sign contracts in the back half of 2023 and into 2024, after the CRA judgment was already on the public registry. Among them was a thirty-year-old barber in Burnaby named Mohammadjavad Nadali.
Mohammadjavad Nadali, $40 a haircut, four years
Nadali charges $40 a haircut. He had spent nearly four years saving the $38,295 he used as the down payment on a one-bedroom at Eclipse in 2023. In an affidavit filed in BC Supreme Court he put his position simply:
"If I knew that the developer owed $12 million to Canada Revenue Agency, I would never have purchased that unit. Knowing any of these facts I would view the developer as not responsible, and I would not purchase from them."
He did not know, when he signed, that the CRA had registered a judgment three months earlier. He did not know about the alleged GST misappropriation. He did not know (because nothing in his disclosure statement told him) that the developer was negotiating with KingSett over multi-site defaults. He did not know that, fifteen months later, the project would enter creditor protection.
What he did know was that the tower he had bought into would, the marketing said, complete in 2026.
Today Nadali's tower is finished in Brentwood. The building has an occupancy permit. He is one of more than three dozen buyers who have asked the BC Supreme Court, through two coordinated petition groups with letters to the KSV monitor sent in December 2025 and February 2026, to declare their contracts unenforceable on the grounds that the developer failed to disclose material facts.
The court-appointed monitor, KSV Restructuring Inc.(now AlixPartners Restructuring), has characterized the petitions as an end-run around the federal Companies' Creditors Arrangement Act. In its own filings, KSV concedes that the Eclipse presale purchasers agreed to pay "substantially above what could be achieved for the same units in the current market," but argues that allowing them to back out "would encourage further challenges to closings by other pre-sale purchasers, resulting in additional value erosion" and warns that "the impact on the debtors and their creditors ... will be severe."
KingSett's loan-and-portfolio-management director, Daniel Pollack, has filed an affidavit pointing to "uncertainty in the economy and particularly in the real estate market" as the underlying cause of Thind's tax problems and mortgage defaults.
The market position can be measured against Daljit Thind's own words. In an affidavit sworn in 2024 about a different Thind project, Surrey's District Northwest, he said he did "not believe the deposits for the pre-sold units are at risk as they were sold at a price that is below current market value." The market has, in the time since, caught up to him: enough District Northwest pre-sale customers eventually rescinded their contracts to scuttle a planned sale of that project out of receivership.
Murrayville House, 2018: the precedent that defines the law
The law that decides Nadali's case was written eight years ago, on a different stalled project, in Langley. In October 2017, a 92-unit condominium development in Langley called Murrayville House entered receivership. Its developer, 0981478 B.C. Ltd., owed money to a mortgagee named Forjay Management Ltd., which moved to have the receiver disclaim the presale contracts of forty buyers: buyers who had paid deposits at 2014–2016 prices and stood to take possession at completion if the project had finished as planned.
The case was heard by Madam Justice Shelley Fitzpatrick in the BC Supreme Court. Her decision, Forjay Management Ltd. v. 0981478 B.C. Ltd., 2018 BCSC 527, is the controlling authority on what happens to BC presale buyers when their developer goes under.
The decision turned on a single clause that appears in essentially every BC presale contract:
"This Agreement creates contractual rights only and does not create any interest in land."
That clause, the Court found, defines the buyer's place in the priority queue when a project enters receivership: the buyer is an unsecured contractual creditor, not the owner of an interest in real property. The mortgagee (in Murrayville's case, Forjay; in Eclipse's case, KingSett) has legal priority. The receiver may therefore disclaim the presale contracts, return the buyer's deposit with interest, remarket the units at current value, and use the proceeds to pay down the senior lender's secured debt.
Justice Fitzpatrick acknowledged the human stakes directly:
"First, let me state the obvious — there are no winners in these circumstances. I have great sympathy for the position of the pre-sale purchasers who have become embroiled in this litigation and who have now potentially lost the ability to obtain what they hoped would be their homes."
She then ruled against them. The Murrayville buyers received deposits returned with interest, plus a right of first refusal to repurchase their units at the new (substantially higher) market price. Most did not exercise the right.
In the District Northwest receivership, another Thind property, the receiver's sales process gave existing presale purchasers a right to back out, a much larger pool of buyers facing the same question.
For most of the Eclipse buyers, this is the outcome the monitor's lawyers will argue for. It is also, on the bare numbers, not the worst possible result: deposit back, interest, an option to repurchase if the market value supports it. The losses are the lost time, the lost capital appreciation, and, for buyers like Nadali, the loss of the actual home they thought they had bought.
REDMA section 16: the door the court opened
The Eclipse applicants did not rely on Forjay. They built their case on a different statute: the Real Estate Development Marketing Act, SBC 2004, c. 41. Section 16 of REDMA imposes a continuing disclosure obligation on developers. If a developer becomes aware that its disclosure statement does not comply with the Act, or contains a misrepresentation, it is required to immediately file an amendment with the Superintendent and, within a reasonable time, deliver the amendment to each purchaser whose title has not yet completed.
A "material fact" under REDMA is defined to include (a) "a fact, or a proposal to do something, that affects, or could reasonably be expected to affect, the value, price, or use of the development unit or development property"; (b) "the identity of the developer"; and, directly relevant to Eclipse, (c) "the appointment, in respect of the developer, of a receiver, liquidator or trustee in bankruptcy." A "misrepresentation" includes both false statements and omissions of material facts.
The leading BC case applying section 16's amendment-and-delivery framework is Woo v. Onni Ioco Road Five LP, decided by the BC Court of Appeal in 2014. Woo established the test for post-closing rescission under REDMA section 21(3): the undisclosed fact must be objectively material and adversely affect the purchaser. On the facts of Woo itself, the Court of Appeal rejected the purchasers' rescission claim: the undisclosed facts in that case did not meet the materiality-plus-adverse-effect threshold. Woo is, in other words, both the doctrinal framework the Eclipse plaintiffs must work through and a reminder that BC courts have set a high bar for what counts.
The Eclipse applicants' argument was straightforward, and on August 25, 2026 the court accepted it. Justice Masuhara found that the developer had not disclosed, in time, four things it knew: the $12 million CRA judgment, the suspension of the home-warranty coverage, the suspension of the building permit and the halt to construction, and the slipping completion date. Each, he held, was a material fact: something that could reasonably be expected to affect the value, price or use of a unit. Some of them did not reach the disclosure record until the monitor's fifth amendment in November 2025, ten months into the creditor-protection proceeding.
Because the developer did not amend its disclosure statement as section 16 requires, section 23 made the applicants' presale agreements unenforceable against them, from the moment of the breach, which came before the creditor protection began. The court rejected the argument that the federal insolvency statute overrides REDMA: the two work side by side (2026 BCSC 1598, paras. 81 to 112 and 137 to 141).
Unenforceable is not the same as void. The ruling means the developer cannot make these buyers close; it does not cancel the contracts, and it does not decide the deposits. That is a separate hearing, and a harder one than it sounds: the court found most of the deposits were not sitting in trust but had been released to fund construction under the developer's deposit insurance (para. 115).
The frustration door, by contrast, is closed
For BC presale buyers who are simply unhappy with the price decline, BC law leaves essentially no exit. The doctrine of frustration of contract in BC requires that performance be impossible, not merely uneconomic, not merely painful, not merely a substantial loss. The BC Real Estate Association's legal-update materials are unusually direct on this: "Mere financial hardship, market decline, or even substantial price drops between contract signing and completion do not constitute frustration of a presale contract."
I have searched the BC court record for any presale-purchaser frustration case successfully argued since 2020. I have not found one. A buyer who locked in at $900,000 in 2022 and is now being asked to close at $720,000 of market value has no frustration claim. The doctrine does not reach a price decline, however severe.
The other narrow doors (the seven-day rescission period under REDMA s. 21, the negotiated assignment sale to a third party, the defaulted-and-forfeited deposit) are all available, but each is more constrained than most public commentary suggests. The seven-day window has expired for any 2021–2023-era buyer. The assignment market for distressed BC presales has collapsed; what assignment sales still close typically do so at 25–30 percent below original presale price (data from current distressed projects at Chloé and similar). The defaulted-deposit exit is clean only if the buyer's specific contract does not give the developer the right to sue for damages above the deposit if the unit later resells at a loss; some BC contracts give exactly that right. Read your contract before you walk.
The bigger graveyard
The Eclipse case will set the precedent. The list of stranded buyers waiting for the precedent is large.
Across Thind's portfolio, District Northwest in Surrey (a 1,023-unit project) entered receivership in November 2024; its presale rescissions have already exceeded the Shareholder Agreement cap, and the BM Group stalking-horse $86-million bid was terminated in May 2025. Highline at Metrotown and Minoru Square in Richmond entered receivership in December 2024; Highline alone carried a $74.9-million KingSett balance as of November 2025.
Outside the Thind portfolio, The Curv, a 60-storey downtown Vancouver tower from Brivia Group, faced a receivership application from an RBC-led lender syndicate in July 2025; the project never broke ground, against $91.2 million owed. Chloé, a 46-unit Kerrisdale building by Matchpoint Development / Lightstone, entered receivership in February 2025: 31 units presold, only 22 closed, $77.3 million in secured debt and another $1.5 million unsecured. The Met in Port Coquitlam was sold under court-supervised receivership to NorthStar Development (agreement signed September 2024, court-approved at $11.6 million in November 2024); it was relaunched as LIVY. Ardea, a 204-unit Wesgroup project at Vancouver's River District, was cancelled outright in September 2025.
Each carries its own group of stranded presale buyers. Each will look to whatever the BC Supreme Court does with the Eclipse petitions for its template.
What an assignment-holder can actually do
If you hold a BC presale assignment in distress today, the practical options are narrower than most coverage suggests:
- If your project is in formal receivership or CCAA: where the developer's disclosure was in order, the Forjay framework still controls, and the likely outcome is deposit back with interest and a right of first refusal at the new market price. If that price is below your contract price, take the deposit and walk; if it is genuinely affordable at today's value, the right of first refusal is worth a serious look. Where the developer left a material fact out of its disclosure amendments, Eclipse (2026 BCSC 1598) shows that section 23 of REDMA can make your contract unenforceable against you even inside the insolvency. Either way, find out first whether your deposit is in trust or was released under deposit insurance: it decides who you claim it from.
- If your project is not in formal receivership but you suspect material non-disclosure: the REDMA section 16 path is open, and Eclipse is now the worked example. The cost of building that case is real: months of litigation, real legal fees, no guarantee of success. The upside is that a successful challenge makes the contract unenforceable against you, so the developer cannot make you close; what happens to your deposit is a separate question. Engage a real-estate-litigation lawyer with insolvency experience before you do anything else.
- If your project is solvent and you just want out because prices fell: BC law does not provide an exit on those grounds. Your options are negotiated walkaway (developer's discretion), assignment sale (likely at a substantial loss), or default and forfeit. Read your contract carefully, and have a lawyer read it, before defaulting, because some BC presale contracts give the developer the right to sue for damages above the deposit if the unit later resells at a loss.
- The seven-day rescission period under REDMA s. 21 is the cleanest exit ever offered to a BC presale buyer. It has long since expired for any contract signed before mid-2024.
- One closing reminder: under the BC Financial Services Authority trust-account rules, your deposit was supposed to sit in a notary, lawyer or brokerage trust account rather than with the developer. A deposit held that way generally sits outside the bankruptcy estate, which is why the Forjay framework points to buyers getting it back with interest. The exception is deposit insurance: with it, a developer may spend deposits on construction, and at Eclipse about $21 million of $24.4 million was spent that way (2026 BCSC 1598, para. 21). What the court is deciding is the route and the timing, and on the Forjay pattern the money comes back through the receiver alongside a right of first refusal on the unit at a price many buyers will not be able to meet.
Two of those choices turn on the same missing figure: what the unit (or the assignment position itself) would fetch on today's market. The right of first refusal in option 1 is only worth exercising if today's value makes it a sound buy; the assignment sale in option 3 is only worth choosing over default once you know how deep the loss runs. That is a valuation question, not a legal one, and it is the part of this I can answer directly: send me the project and the unit, and I will work out what the position is worth now and which way the arithmetic points.
The precedent, and what comes next
Justice Fitzpatrick's words from 2018 about the Murrayville buyers ("there are no winners in these circumstances") apply equally to Nadali and the other Eclipse petitioners. They will not, regardless of the outcome, get the home they thought they were buying. On August 25, 2026 the court gave them the best realistic result on the contracts: unenforceable against them. It did not give them their money back. That is the next hearing.
The decision now tells every other stranded BC presale buyer, and every BC developer who kept selling while an insolvency was building, where the line sits: fail to amend the disclosure statement when material facts arrive, and the contracts cannot be enforced against the buyers who were kept in the dark.
For Nadali, who put down $38,295 in 2023, the open question is now the deposit: whether it comes back from the part still held in trust, through the deposit insurer, or not at all, and on what terms. The court left that for a separate hearing.
His tower is finished. Its occupancy permit is dated April 10, 2026.
His first hearing came in June 2026. The next one is about his money.
This piece pairs with the four-year contour line: same story, from outside the courtroom.
I’m Bronson Job, a REALTOR® with Momentum Realty Inc. I’m not the developer’s sales team. I can work out what your unit is worth today, as your REALTOR®.
Ask
Holding a contract in a stalled tower?
What the unit and the assignment position are worth on today's market is the figure most exits turn on, and it is a market question rather than a legal one. The project, the unit and your contract price are enough to start. Eclipse at Lumina Brentwood (assignment or presale).
Verified sources (4)· re-verified Oct 16, 2026Show sources
Every claim on this page is sourced to a primary government, regulator, or industry-association URL. We re-verify quarterly; the verification dates below show when each source was last confirmed against the live government page.
- CRAretrieved Oct 16, 2026GST/HST Info Sheet GI-120: Assignment of a Purchase and Sale Agreement for a New House or Condominium Unithttps://www.canada.ca/en/revenue-agency/services/forms-publications/publications/gi-120/assignment-a-purchase-sale-agreement-a-new-house-condominium-unit.html
- Government of Canadaretrieved Aug 2, 2026GST/HST Notice 323 — Treatment of Assignment Saleshttps://www.canada.ca/en/revenue-agency/services/forms-publications/publications/notice323/proposed-gst-hst-treatment-assignment-sales.html
- CRAretrieved Aug 2, 2026Principal residence and other real estate (flipped property rules)https://www.canada.ca/en/revenue-agency/services/tax/individuals/topics/about-your-tax-return/tax-return/completing-a-tax-return/personal-income/line-12700-capital-gains/principal-residence-other-real-estate.html
- BC Governmentretrieved Aug 2, 2026Speculation and vacancy tax exemptionshttps://www2.gov.bc.ca/gov/content/taxes/speculation-vacancy-tax
bc.presale.assignment_tax_treatment · v1View in Codex →Verified sources (2)· re-verified Aug 2, 2026Show sources
Every claim on this page is sourced to a primary government, regulator, or industry-association URL. We re-verify quarterly; the verification dates below show when each source was last confirmed against the live government page.
- BCFSAretrieved Aug 2, 2026Material Latent Defectshttps://www.bcfsa.ca/public-resources/real-estate/selling-home/material-latent-defects
- BC Governmentretrieved Aug 2, 2026Real Estate Services Rules, BC Reg 209/2021 — s. 59https://www.bclaws.gov.bc.ca/civix/document/id/complete/statreg/209_2021
bc.mld_disclosure · v2View in Codex →Sources
- CBC News (May 26, 2026): Eclipse pre-sale disputecbc.ca
- CBC News: CRA $11.9M judgment vs Thind affiliatescbc.ca
- Storeys: Eclipse / KingSett creditor protectionstoreys.com
- Storeys: Eclipse path to completionstoreys.com
- Storeys: District Northwest receivershipstoreys.com
- Storeys: Highline and Minoru receivershipsstoreys.com
- Storeys: The Curv / Brivia receivershipstoreys.com
- Storeys: Chloé / Matchpoint receivershipstoreys.com
- Storeys: Quarry Rock / Livy PoCo salestoreys.com
- Insolvency Insider: Beta View Homes / Lumina Eclipse LP CCAAinsolvencyinsider.ca
- Cassels: Forjay Management 2018 BCSC 527 summarycassels.com
- BC Laws: Real Estate Development Marketing Act (REDMA)bclaws.gov.bc.ca
- BCFSA: REDMA FAQsbcfsa.ca
- BCFSA: Presales informationbcfsa.ca
- BCREA Legally Speaking 524: frustration doctrine and presalesbcrea.bc.ca
- McCarthy Tétrault: Woo v. Onni: BCCA rejects post-closing rescissionmccarthy.ca
- Mondaq: Post-closing rescission under REDMAmondaq.com
- Drishti Magazine: Daljit Thind profiledrishtimagazine.com
- BC Government: Order of British Columbia 2023 recipientsnews.gov.bc.ca
- CTV News: Wesgroup cancels Ardeactvnews.ca